Programme Update: October 2016

Project Progress

The Cambium development is progressing well with the piled foundations phase 1 coming to the end in the next four weeks and the drainage and block and brickwork foundations following on with Blocks 3 (11 town Houses), Block 4 (7 town Houses) and Block 5 (12 town houses). The block and brickworks will commence on Block 1 week commencing the 17th October 2016 with Blocks 3, 4 and 5 following on.
The photograph shows the completed foundations and drainage to Block 1 on the Victoria Drive elevation, comprising six town houses the block and brickwork is due to commence on the 17th October 2016.

Construction Programme

  • Current status – week 9 of 106
  • October – Piling 75 % completed on programme
  • November – Drainage, brick and block work to commence. Relocation of marketing suite to Victoria Drive
  • December – Drainage, brick and block work to continue

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s